ITS Service Status Report

Scheduled Maintenance — Resolved

In-building Networks, Electrical Outage AM & PM on 4/22/17 at Institute for Social Research (ISR)

Start Time: 04/22/2017 7:00 am

Maintenance Completed: 04/22/2017 2:02 pm

Saturday, 4/22/17 from 07:00 to 17:00, there will be an electrical shutdown that will affect the: Air Conditioner; Computer Rm (needs to be reset after shutdown); and DDC Control Panel (needs to be backed up prior to electrical shutdown).
Elevators-4 Substation 3 will be in service during this time.

Purpose of Shutdown: 5 year preventative maintenance to the substation and the cable refeed for the Trotter House Construction Project at ISR. T

The buildings should not be occupied during this time due to lighting, ventilation, networking, elevator, and life safety system service interruptions. All sensitive electronic equipment should be turned off or unplugged. You may want to empty any refrigerators prior to this date.

Issue Symptoms: Outage

Technical Details

Service Type: Production

Comments:
All ITS and Plant IT network devices are back online.

Groups Notified:

Report Additional Impacts