ITS Service Status Report

Scheduled Maintenance — Resolved

In-building Networks, Mosher Jordan

Start Time: 08/19/2017 7:00 am

Maintenance Completed: 08/28/2017 9:54 am

Purpose of Shutdown: To perform the 5 year preventative maintenance to the Substation. This maintenance is required to be performed every five years and will result in a total power outage

Issue Symptoms: Intermittent issues

Technical Details

Service Type: Production

Comments:
Maintenance completed

Groups Notified:

Report Additional Impacts