ITS Service Status Report

Scheduled Maintenance — Resolved

Data Center Services

Start Time: 01/13/2018 11:00 pm

Maintenance Completed: 01/14/2018 1:10 am

On 1/13/18 we will be moving the management interface on the MACC datacenter ASAs. This is interface is only for management traffic, networks hosted on the firewall should be unaffected.

Issue Symptoms: None

Technical Details

Service Type: Production

Server Name: fw-macc-1 fw-macc-1-stby

Comments:
Maintenance completed as expected.

Groups Notified: