ITS Service Status Report

Scheduled Maintenance — Resolved

Data Center Services

Start Time: 01/15/2018 5:00 am

Maintenance Completed: 01/16/2018 10:54 am

There is no expected user impact.

Issue Symptoms: None

Technical Details

Service Type: Production

Comments:
Three new TOR switches will be installed at MACC and ASBDC. These will be dedicated to a new research project and there is no expected impact to other services in either data-center.

Report Additional Impacts