Unscheduled Outage — Resolved

In-building Networks, Multiple Building Effected by a Blown Transformer

Start Time: 07/14/2018 2:30 am

Service Restored: 07/14/2018 7:37 am

Currently the following building are effected by a blown transformer:
500 East Washington
300 and 400 NIB
214 South State Street
Lane
Glen Avenue Parking Structure
Salt Storage

Issue Symptoms: Outage

Technical Details

Service Type: Production

Comments:
Currently DTE has an estimated restoration time of: Sat Jul 14 2018, 6:15 AM

DTE resolved their issue and power has been restored