ITS Service Status Report

Scheduled Maintenance — Resolved

Electrical Shutdown - EECS

Services Affected: In-building Networks

Start Time: 03/04/2019 6:00 am

Maintenance Completed: 03/04/2019 8:05 am

Issue Symptoms: Inaccessible

3/4/19 08:00am  Maintenance completed, all devices are back online

 

Maintenance is expected to start on March 4, 2019 at 6 AM.
Maintenance is expected to end March 4, 2019 at 8 AM.

This shutdown to the building is necessary to perform electrical work to install two new VFD's to the electrical panel. During this maintenance, WiFi, wired network connections, network phones, printers, etc. will be unavailable.

Once power is restored and we can ensure that all ITS equipment and services are back up and functioning normally, we will close this status

Technical Details

Service Type: Production

Comments:

3/4/19 08:00 Maintenance complete and power restored, no residual equipment issues, all networks are working as expected