Services Affected: In-building Networks, GG Brown - UPS Replacement, 2nd Floor
Start Time: 03/14/2019 5:00 am
Maintenance Completed: 03/14/2019 6:14 am
Issue Symptoms: Degradation
06:14 3/14 The UPS has been replaced and all services have been restored.
We will be replacing a failing UPS unit on the second floor of the GG Brown Building in closet 2139. There will be a brief loss of all network services (VoIP, wired and wireless) on the second floor while equipment is moved to the replacement UPS.
The maintenance window is scheduled from 05:00am to 07:00am on Thursday, March 14th. Services should be down less than 5 minutes during the maintenance window. This status page will be updated upon completion of the maintenance.
Service Type: Production
Comments:
06:14 3/14 The UPS has been replaced and all services have been restored.
We will be replacing a failing UPS in closet 2139 of the GG Brown building.
Groups Notified:
Contact the ITS Service Center for more information or to report additional impacts.