ITS Service Status Report

Scheduled Maintenance — Resolved

GG Brown - UPS Replacement, 2nd Floor

Services Affected: In-building Networks, GG Brown - UPS Replacement, 2nd Floor

Start Time: 03/14/2019 5:00 am

Maintenance Completed: 03/14/2019 6:14 am

Issue Symptoms: Degradation

06:14 3/14 The UPS has been replaced and all services have been restored.

We will be replacing a failing UPS unit on the second floor of the GG Brown Building in closet 2139.  There will be a brief loss of all network services (VoIP, wired and wireless) on the second floor while equipment is moved to the replacement UPS. 

The maintenance window is scheduled from 05:00am to 07:00am on Thursday, March 14th.  Services should be down less than 5 minutes during the maintenance window.  This status page will be updated upon completion of the maintenance.

Technical Details

Service Type: Production

Comments:

06:14 3/14 The UPS has been replaced and all services have been restored.

We will be replacing a failing UPS in closet 2139 of the GG Brown building.

Groups Notified:

Report Additional Impacts

Contact the ITS Service Center for more information or to report additional impacts.