Scheduled Maintenance — Resolved

Electrical Shutdown to North Campus Ground Svc Facility-2514

Services Affected: In-building Networks, Electrical Shutdown to North Campus Ground Svc Facility-2514

Start Time: 11/09/2019 7:00 am

Maintenance Completed: 11/09/2019 12:40 pm

Issue Symptoms: Outage

11/09/19 07:00am-11/09/19 3pm This is notification of an electrical shutdown scheduled at the following building: North Campus Ground Svc Facility

This shutdown is required to perform 5 year preventative maintenance to the Electrical Substation for the NC Chiller Plant and will result in a total power outage affecting the North Campus Ground Svc Facility. During this maintenance, WiFi, wired network connections, network phones, printers, etc. will be unavailable.

Once power is restored and we can ensure that all ITS equipment and services are back up and functioning normally, we will close this status.

Who is Impacted? Students, Faculty, and Staff

Next Update: ITS services returned to normal

Technical Details

Service Type: Production

Comments:

electrical power restored.  ITS networks are back up.