Scheduled Maintenance — Resolved

UPS Replacement - Central Campus Rec Building

Services Affected: In-building Networks, Internet, UPS Replacement - Central Campus Rec Building

Start Time: 07/18/2019 6:00 am

Maintenance Completed: 07/18/2019 7:00 am

Issue Symptoms: Outdated

UMnet will be replacing a failing UPS unit in the CCRB building. The maintenance will be taking place on Thursday July 18 between 05:00 am and 07:00 am in the morning.  

It should take approximately 15 minutes during the scheduled maintenance window and no outage is expected because of the redundant power supplies in the building distribution layer switch.

We will either update or close this status page at the conclusion of this maintenance.

Technical Details

Service Type: Production

Server Name: UPS Replacement - Central Campus Rec Building

Comments:

UPS was replaced,

a brief outage was noticed due to a failed stack member ( replaced from existing spares ) 10.233.41.5 s-ccrb-1084-4