ITS Service Status Report

Scheduled Maintenance — Resolved

Unified power will be testing UPS @Francois-Xavier Bagnoud Building (FXB) in room 1072

Services Affected: Data Center Services, Francois-Xavier Bagnoud Building (FXB)

Start Time: 11/09/2019 11:00 pm

Maintenance Completed: 11/11/2019 7:46 am

Issue Symptoms: None

None 

Who is Impacted? No one should be impacted as all systems will remain in place and on line.

Next Update: 11-09-19 @ 2330

Technical Details

Service Type: Production

Comments:

This is the annual preventative maintenance of the FXB room 1072 ITS data center's backup battery, uninterruptible power system and bypass switch. There will be no interruptions to the system. Backup batteries will be available throughout the entire PM.

 

What we are doing: Unified Power will be performing a complete battery resistant testing phase and will perform the semi-annual preventative maintenance (PM) for the APC uninterruptible power systems (UPS) and UPS battery string. While in service the UPS system will remain in service.

Why we are doing this: Semi-Annual maintenance allows us to see the longevity and life of the battery's. As well as the functionality of the UPS system. 

Who will be impacted:   This service will not jeopardize the compute floor equipment.  All system will remain normal during the entire maintenance. We anticipate no impact to any services running at Francois-Xavier Bagnoud Building (FXB).

Groups Notified:

Report Additional Impacts