Services Affected: In-building Networks, Network Outage across Ann Arbor (North, Central, South)
Start Time: 03/30/2020 10:34 am
Service Restored: 03/30/2020 4:55 pm
Issue Symptoms: Degradation
On Monday, March 30 at 10:34 am There was an unscheduled plant power outage on North Campus. The cause is unknown at this time.
On Monday, March 30 at 12:25 pm Power has been restored to most of the North Campus Buildings, Bursley Building is still down due to Plant is working on restoring power.
On Monday, March 30, at 14:30 Power has been restored to Bursley Building. Beyster Building still has some switches down. Technicians are onsite restoring the switches.
Who is Impacted? Students, Faculty, Staff
Next Update: ITS services returned to normal
Service Type: Production
Comments:
The switches at Beyster are up. There was a damaged UPS in the network closet. The UPS has been bypassed.