ITS Service Status Report

Unscheduled Outage — Service Restored

Plant Power Outage on North Campus Affecting Beyster

Services Affected: In-building Networks, Network Outage across Ann Arbor (North, Central, South)

Start Time: 03/30/2020 10:34 am

Service Restored: 03/30/2020 4:55 pm

Issue Symptoms: Degradation

On Monday, March 30 at 10:34 am There was an unscheduled plant power outage on North Campus. The cause is unknown at this time.

On Monday, March 30 at 12:25 pm Power has been restored to most of the North Campus Buildings, Bursley Building is still down due to Plant is working on restoring power.

On Monday, March 30, at 14:30 Power has been restored to Bursley Building. Beyster Building still has some switches down. Technicians are onsite restoring the switches.

Who is Impacted? Students, Faculty, Staff

Next Update: ITS services returned to normal

Technical Details

Service Type: Production

Comments:

The switches at Beyster are up.  There was a damaged UPS in the network closet.  The UPS has been bypassed.

Groups Notified:

Report Additional Impacts

Contact the ITS Service Center for more information or to report additional impacts.