ITS Service Status Report

Scheduled Maintenance — Canceled

Move power for Core Router @ Cooley Mortimer E Building

Services Affected: Data Center Services, Cooley Mortimer E Building

Start Time: 05/23/2020 11:00 pm

Issue Symptoms: None

None 

Who is Impacted? No one should be impacted as all systems will remain in place and on line.

Next Update: 05/24/2020 @ 2300

Technical Details

Service Type: Production

Server Name: None

Comments:

Moving the power of the Core router at Cooley will be done in stages and is redundantly fed off of house and UPS power with generator backup. I will move the normal power first. Once completed I will transition over to the generator to do the UPS power. This will allow us to have no seen power issues. Once completed I would put the system back on normal power.