Scheduled Maintenance — Resolved

UPS replacement - Wolverine Tower 3rd Floor

Services Affected: In-building Networks, UPS replacement - Wolverine Tower 3rd Floor

Start Time: 09/17/2020 5:00 am

Maintenance Completed: 09/17/2020 9:17 am

Issue Symptoms: Intermittent issues

UMNet will be replacing an external battery power (UPS) at the Wolverine Tower on the 3rd Floor.


The activity performed will result in upgrading a critical device that provides uninterrupted power to the network in case a short power outage or surge occurs.

This will impact any wired & wireless networking technologies on the 3rd floor for faculty, staff and students, including but not limited to desktops, laptops, network phones, and printers.

It is recommended to have an alternative plan of working from a different floor/location during the planned AM maintenance window and/or forward your phone calls to another extension during the same period of time.


The maintenance is scheduled for Thu, Sep 17th between the hours of 5 am - 7 am. The actual work is expected to take less than 20 minutes however, the 2 hours maintenance window is reserved.

We will update this page once the new UPS is operational or at the end of the maintenance window.

Who is Impacted? Students, Faculty, Staf

Next Update: 9/17/2020 08:00

Technical Details

Service Type: Production

Comments:

UPS replaced