ITS Service Status Report

Scheduled Maintenance — Resolved

Research Switch Reconfiguration at the MACC

Services Affected: OSiRIS project

Start Time: 07/31/2021 11:00 pm

Maintenance Completed: 08/01/2021 12:10 am

Issue Symptoms: None

Engineering and UMnet will be reconfiguring the OSiRIS research switch uplinks at the MACC to L3 with BGP peerings

There is no expected impact to other services in the MACC

Who is Impacted? No impact to campus is expected

Next Update: 7/31/21 @ 11:59 pm

Technical Details

Service Type: Production

Server Name: r-MACC-C & r-MACC-D

Comments:

Changes were applied as planned.  Systems were verified as working.

Groups Notified:

Report Additional Impacts