Services Affected: Data Center Services
Start Time: 01/22/2022 7:00 pm
Maintenance Completed: 01/22/2022 8:05 pm
Issue Symptoms: None
ITS Engineering and UMnet will be removing power and restarting the d-ncasdn-2 router to verify power failure recovery.
No outage is expected due to the redundancy design of the data node routers.
We will update this status page when the test has been completed or at the end of the maintenance window.
Who is Impacted? No impact to campus is expected
Next Update: When the work has been completed
Service Type: Production
Server Name: d-ncasdn-2
Comments:
1/22/22 @ 8:05 pm - Maintenance event completed successfully and logged data was collected for analysis.