ITS Service Status Report

Scheduled Maintenance — Resolved

MACC Data Center Cleaning

Services Affected: Data Center Services

Start Time: 06/20/2022 9:00 am

Maintenance Completed: 06/25/2022 10:15 am

Issue Symptoms: None

 

What we are doing: Cleaning of the MACC Data Center floor. Includes under the floor vacuuming and cleaning/polishing of the raised floor. Outside surface of AC units, top of racks, and end row rack panels will be wiped down. We will not be opening or going inside any racks.

Why we are doing this: To maintain a clean, professional looking, and operational data center environment.

Who will be impacted: There will be no impact to any services.

Who is Impacted? No impact

Next Update: 6/24 4:00 pm

Technical Details

Service Type: Production

Comments:

The data center has been cleaned.

Report Additional Impacts

Contact the ITS Service Center for more information or to report additional impacts.