ITS Service Status Report

Scheduled Maintenance — Maintenance Completed

Distribution Layer (DL) switch replacement in Ruthven and the Central Campus Classroom (CCCB) buildings.

Services Affected: In-building Networks, Internet, Voice Services

Start Time: 04/01/2023 8:00 am

Maintenance Completed: 04/01/2023 1:55 pm

Issue Symptoms: Outage

ITS Engineering and UMnet will be replacing the Distribution Layer (DL) switches located in the Ruthven and the Central Campus Classroom (CCCB) buildings  .

A new Cisco DL switch will be installed in each building prior to the cutover date and connected to the new 100G core backbone.

On the day of the cutover, FSU will transfer all the endpoint connections from the old DL switches to the new DL switches which have been populated with configuration information via automation.

The actual work is expected to take up to 8 hours with a portion of the maintenance window reserved for testing.

Who is Impacted? Network Users in Ruthven and the CCCB buildings

Technical Details

Service Type: Production

Server Name: d-ruthven-1, d-ruthven-2

Comments:

4/1/23 @ 11:00 am - All Access Layer switches have been migrated to the new DLs.

4/1/23 @ 1:55 pm - Maintenance completed.

Groups Notified:

Report Additional Impacts

Contact the ITS Service Center for more information or to report additional impacts.