ITS Service Status Report

Scheduled Maintenance — Maintenance Completed

Network Border Infrastructure System (NBIS) Update

Services Affected: NBIS

Start Time: 04/03/2023 9:00 am

Maintenance Completed: 04/03/2023 11:22 am

Issue Symptoms: Outage

ITS Network Security Operations will be updating the software on the NBIS Corelight servers.

The actual work is expected to take approximately 2 hours to complete, however additional time is reserved for testing.

Who is Impacted? No noticeable impact to campus is expected.

Technical Details

Service Type: Production

Server Name: bsec-ap3k-sebdn-1, bsec-ap3k-sebdn-2, bsec-ap3k-aldn-1, bsec-ap3k-aldn-2

Comments:

Maintenance has been completed for version 

  • 27.2.1

Groups Notified:

Report Additional Impacts

Contact the ITS Service Center for more information or to report additional impacts.